9 districts Min residential lot 1–10 ac Central Hudson

Residential lots in the Town of Union Vale run from a 1-acre minimum in Residential 1 District up to 10 acres in Rural Development 10 District, across 9 zoning districts in all. Short-term rentals allowed with local rules. Power here is Central Hudson territory. The district table below has the setbacks, height limits and coverage - confirm the specifics with the building department at (845) 724-5600 before you rely on a figure.

Looking specifically at an accessory dwelling unit? See ADU rules for Union Vale →

Zoning districts

District Min lot Setbacks F / S / R Max height ADU
Rural Development 10 District 10 ac 100 / 75 / 100 ft 35 ft Special permit
Residential Agricultural 5 District 5 ac 100 / 50 / 100 ft 35 ft Special permit
Residential Agricultural 3 District 3 ac 75 / 35 / 50 ft 35 ft Special permit
Residential 1.5 District 1.5 ac 50 / 35 / 40 ft 35 ft Special permit
Residential 1 District 1 ac 35 / 35 / 35 ft 35 ft Special permit
Hamlet District 1.5 ac 40 / 25 / 40 ft 35 ft Special permit
Neighborhood Commercial District 1 ac 40 / 25 / 40 ft 35 ft Special permit
Town Center District 20 / 25 / 80 ft 35 ft No
Airport District 2.5 ac 100 / 50 / 50 ft 35 ft No

Rural Development 10 District — Lot frontage and lot width at the building line are both 375 ft. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 75 ft front, 50 ft side, 50 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 85% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Residential Agricultural 5 District — Lot frontage and lot width at the building line are both 275 ft. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 60 ft front, 25 ft side, 40 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 80% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Residential Agricultural 3 District — Lot frontage and lot width at the building line are both 225 ft. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 45 ft front, 20 ft side, 25 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 75% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Residential 1.5 District — Lot frontage and lot width at the building line are both 175 ft. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 30 ft front, 20 ft side, 20 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 70% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Residential 1 District — Lot frontage and lot width at the building line are both 150 ft. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 25 ft front, 20 ft side, 15 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 65% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Hamlet District — Lot frontage and lot width at the building line are DIFFERENT: 100 ft of frontage but 150 ft of width at the building line, so a lot that fronts the road adequately can still be too narrow where the house goes. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 25 ft front, 15 ft side, 15 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 50% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Neighborhood Commercial District — Lot frontage and lot width at the building line are DIFFERENT: 100 ft of frontage but 150 ft of width at the building line, so a lot that fronts the road adequately can still be too narrow where the house goes. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 30 ft front, 15 ft side, 30 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 40% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Town Center District — TC publishes NO minimum lot area for a residential lot — the schedule sends you to Note A, which states there is none, and sets the residential density instead at one dwelling unit per half acre before any approved density bonus. A COMMERCIAL lot in TC does have a minimum, of two acres, and a commercial building footprint is capped at 2,500 sq ft, raised to 4,000 sq ft for food and grocery store uses (Note 7). The front setback is a RANGE, not a minimum: 20 ft minimum and 35 ft MAXIMUM, so a building may not be set further back than 35 ft. The 25 ft side yard, and the 20 ft parking side setback, may be cut to ZERO for zero-lot-line development authorised by special use permit where emergency vehicle access is adequate (Note 3) — the trigger is that kind of development rather than the permit alone, so it is stated here rather than as a separate set of standards that any application reaching the Planning Board would qualify for. Residential development fronting Route 55 must devote at least 15% of total building square footage to commercial uses, and the last 25% of dwelling units get no certificate of occupancy until that commercial component is complete (Note 5). Commercial, multifamily, townhouse and mixed-use development must also meet the TC Design Standards at § 210 Attachment 3 (Note 6). Lot frontage and lot width at the building line are both 75 ft. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 20 ft front, 20 ft side, 30 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 50% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Airport District — Lot frontage and lot width at the building line are DIFFERENT: 100 ft of frontage but 200 ft of width at the building line, so a lot that fronts the road adequately can still be too narrow where the house goes. Parking areas and access driveways have a complete second set of setbacks, separate from the building setbacks above: 35 ft front, 15 ft side, 20 ft rear. Parking is barred from any front yard setback and must go to the rear or side of the principal building, with landscaping and screening under § 210-25B (Note 4). A minimum of 35% of the lot must be left as open space, which is a separate test from the coverage cap. These standards apply to permitted uses; Article VI may set extraordinary standards for special permit uses (Note 1). They are not controlling on municipal uses on municipal property (Note 2). Coverage is BUILDING coverage — the composite footprint of all principal and accessory structures, excluding uncovered porches, terraces and steps.

Short-term rentals

Short-term rentals allowed with local rules. Short-term rental is a defined and regulated use. § 210-85A of Zoning Chapter 210 defines SHORT TERM RENTAL as 'an accessory use or supplementary business in a dwelling unit' letting it for less than 30 days, and ACCESSORY USE is separately defined as customarily incidental and subordinate to the principal use on the same lot. New York State's 2025 short-term rental registry (Ch. 99 of the Laws of 2025) separately requires every host statewide to register the unit regardless of local law. Confirm with Town of Union Vale at (845) 724-5600 before listing.

Good to know

Working out a budget? A standard-finish build here runs $215–$282/sq ft , and a conforming lot adds about $22,425 on top - see the full cost to build a house in Union Vale, or what an ADU costs here.

Sizing up a specific parcel in Union Vale?

Aldo pulls the exact zoning district, setbacks, and build feasibility for any parcel — before you buy. Enter your email to open Aldo and run your free report.

Other Dutchess County towns

Zoning figures for Town of Union Vale are compiled from the municipal code (last reviewed 2026-08-16) and provided for decision-support only - not legal, engineering, or architectural advice. Setback and dimensional standards often carry conditions and exceptions; verify with the building department at (845) 724-5600 before relying on any number. Source: Offsite / Aldo zoning dataset, municipalData.js.

Building outside these counties?

Aldo covers 10 Hudson Valley & Capital Region counties today. Tell us your market — we'll build the zoning + feasibility data for it.