Village of Rhinebeck, NY: zoning for new construction

5 districts Min residential lot 0.1837 ac Central Hudson

The Village of Rhinebeck sets a residential minimum of about 0.1837 acres in Residential, one of its 5 zoning districts. Short-term rentals allowed with local rules. Power here is Central Hudson territory. The district table below has the setbacks, height limits and coverage - confirm the specifics with the building department at (845) 876-7039 before you rely on a figure.

Looking specifically at an accessory dwelling unit? See ADU rules for Rhinebeck →

Zoning districts

District Min lot Setbacks F / S / R Max height ADU
Village Center 0.0918 ac 0 / 0 / 10 ft 40 ft Special permit
Residential 0.1837 ac 10 / 10 / 10 ft 35 ft Special permit
Gateway Business 0.3444 ac 20 / 20 / 10 ft 35 ft No
Medical and Professional 0.1837 ac 10 / 10 / 10 ft 35 ft Special permit
Fairgrounds 3 ac 25 / 25 / 25 ft 35 ft No

Village Center — The front yard is a RANGE, not a minimum: 0 ft minimum and 5 ft MAXIMUM. A building may not be set further back than the maximum, which is a build-to line. Village Center is the one district with a MAXIMUM SIDE yard as well as a maximum front yard: a building may not sit more than 25 ft from the side lot line. Inside the Special Sensitivity Overlay the Village Center takes a different column entirely — a 10 ft minimum and 25 ft maximum front yard, a 10 ft minimum side yard and no side maximum — while the lot area, frontage, width, height and coverage stay the same. Minimum lot frontage is 40 ft, published separately from the 40 ft lot width. Where two properties are separated by a district boundary, the LARGER of the two required yards applies to both, whichever type of yard it is (§ 120-10). Eaves and similar building features may encroach up to 3 ft into a front yard. A sight triangle must be kept clear 25 ft in both directions from a street corner and 10 ft from a driveway curb cut (§§ 120-11, 120-12).

Residential — The front yard is a RANGE, not a minimum: 10 ft minimum and 25 ft MAXIMUM. A building may not be set further back than the maximum, which is a build-to line. The Planning Board may instead let a structure be built anywhere within the setbacks of the two adjacent structures on the same side of the street, measured from the street; a corner lot may average the adjacent lot on each side. Parcels in the Bulkeley Schoolhouse Overlay District take the dimensional standards at § 120-39.1D instead of these. Minimum lot frontage is 60 ft, published separately from the 60 ft lot width. Where two properties are separated by a district boundary, the LARGER of the two required yards applies to both, whichever type of yard it is (§ 120-10). Eaves and similar building features may encroach up to 3 ft into a front yard. A sight triangle must be kept clear 25 ft in both directions from a street corner and 10 ft from a driveway curb cut (§§ 120-11, 120-12).

Gateway Business — The front yard is a RANGE, not a minimum: 20 ft minimum and 40 ft MAXIMUM. A building may not be set further back than the maximum, which is a build-to line. Minimum lot frontage is 75 ft, published separately from the 75 ft lot width. Where two properties are separated by a district boundary, the LARGER of the two required yards applies to both, whichever type of yard it is (§ 120-10). Eaves and similar building features may encroach up to 3 ft into a front yard. A sight triangle must be kept clear 25 ft in both directions from a street corner and 10 ft from a driveway curb cut (§§ 120-11, 120-12).

Medical and Professional — The front yard is a RANGE, not a minimum: 10 ft minimum and 25 ft MAXIMUM. A building may not be set further back than the maximum, which is a build-to line. Minimum lot frontage is 70 ft, published separately from the 70 ft lot width. Where two properties are separated by a district boundary, the LARGER of the two required yards applies to both, whichever type of yard it is (§ 120-10). Eaves and similar building features may encroach up to 3 ft into a front yard. A sight triangle must be kept clear 25 ft in both directions from a street corner and 10 ft from a driveway curb cut (§§ 120-11, 120-12).

Fairgrounds — The Fairgrounds District is excluded from the Dimensional Table; its standards are in § 120-38G. The 25 ft front figure is the ROUTE 9 setback, and it rises to 75 ft where the parcel is adjacent to a residential district. Minimum lot frontage and minimum lot width are both 200 ft. Beside the 20% building coverage there is a 40% MAXIMUM IMPERVIOUS coverage, which is the limit parking and drives count against. Every building and zoning permit needs site plan approval under Article XI, and the improvements and lot lines shown on the As-Built Survey and Fairgrounds District Map are deemed conforming. A buffer zone on that map allows only temporary parking, roads and driveways, and requires new utility lines to be placed underground. Where two properties are separated by a district boundary, the LARGER of the two required yards applies to both, whichever type of yard it is (§ 120-10).

Short-term rentals

Short-term rentals allowed with local rules. Highly regulated per § 120-17.1. Annual permit + Planning Board approval required. Owner-occupied primary residence only. Maximum 15 permits issued annually. Unhosted rentals require designated 24/7 local property manager. Max 16 rental days/yr with minimum 7-day gaps between bookings. Max 6 guests for 2-bedroom unit. Contact Village Clerk at (845) 876-7039.

Good to know

Working out a budget? A standard-finish build here runs $215–$282/sq ft , and a conforming lot adds about $13,308 on top - see the full cost to build a house in Rhinebeck, or what an ADU costs here.

Sizing up a specific parcel in Rhinebeck?

Aldo pulls the exact zoning district, setbacks, and build feasibility for any parcel — before you buy. Enter your email to open Aldo and run your free report.

Other Dutchess County towns

Zoning figures for Village of Rhinebeck are compiled from the municipal code (last reviewed 2026-08-16) and provided for decision-support only - not legal, engineering, or architectural advice. Setback and dimensional standards often carry conditions and exceptions; verify with the building department at (845) 876-7039 before relying on any number. Source: Offsite / Aldo zoning dataset, municipalData.js.

Building outside these counties?

Aldo covers 10 Hudson Valley & Capital Region counties today. Tell us your market — we'll build the zoning + feasibility data for it.